Обзор проекта
A 1,900 MW combined-cycle gas turbine power plant delivered on a full EPC basis, including balance of plant, seawater cooling intake, 380 kV GIS switchyard and grid interconnection.
Объём работ
Engineering, procurement, construction, commissioning and performance testing of three power blocks; heavy civil works; marine intake/outfall; HV transmission interface.
Инженерный вызов
Executing heavy lifts and precision turbine alignment in 50°C ambient conditions while maintaining an accelerated 42-month schedule across 6,000+ multinational workforce.
Решение Sayın
4D BIM-integrated planning, modular pre-assembly of pipe racks, night-shift concrete strategy and digital progress monitoring reduced critical-path risk and kept the program 6 weeks ahead.